Warfield SPD Stages
The Warfield Supplementary Planning Document (SPD) will follow various stages during its production. Each stage will be accompanied by a sustainability appraisal to assess and guide the preparation of the document. The key stages of production are:
Pre production/issues and options
| Document/Action | Timescale | Sustainability Appraisal |
| Evidence gathering, background research and stakeholder engagement | September 2009 - May 2010 | |
| January 2010 | Consultation Sustainability Appraisal Scoping Report |
Publication of draft submission
| Document/Action | Timescale | Sustainability Appraisal |
| Public Participation on Draft Submission SPD | December 2010 | Consultation on Sustainability Appraisal Report |
| Consider responses/Finalise SPD/SA | Finalise Sustainability Appraisal Report |
Adoption
| Document | Timescale | Sustainability Appraisal |
| Adoption and publication of the Warfield SPD | 2011 | Final Sustainability Appraisal Report |