Mill Lane Footbridge Schedule

February - March 2008

Continuation of construction of bridge foundations – pile caps, abutments and approach ramps.

April 2008

Completion of the abutments and approach ramps to the new footbridge.

May 2008

Installation of the new footbridge and demolition of the existing bridge.  Pedestrians will be transferred onto the new bridge at the end of May.

Weekend closures of Mill Lane between its roundabout junctions with Ringmead and Wildridings Road and its roundabout junctions with South Hill Road and Great Holland’s Road on 3 - 4 May and 31 May – 1 June.

June 2008

Site demobilisation and landscaping of the area.

July 2008

Opening of the new footbridge.


-Listen to this page- -Listen- -Feedback on this page- -Feedback- -Print this page- Print


top

External Links

  • Bracknell Forest Council is not responsible for the content of external websites

Contacts

Customer Services
Tel: 01344 352000
Email: customer.services
@bracknell-forest.gov.uk


Location and Opening Times
Skip to main content
[
Home
]
[
What's New
]
[
Sitemap
]
[
Search
]
[
Frequently Asked Questions
]
[
Website Help
]
[
Complaints Procedure
]
[
Disclaimer
]
[
Feedback Form
]
[
Accessibility
]
[
Skip to main content
]