Utility companies - performance statistics
The street authority is empowered to inspect a percentage of statutory undertakers' (utilities) works (sample inspections). These inspections are completed at different stages of the life of the works or the subsequent reinstatement. These stages are explained below:
| Categories | Explanation |
|
A |
Undertaken during the progress of works |
|
B |
Undertaken within the 6 months following interim or permanent reinstatement |
|
C |
Undertaken within the 3 months preceding the end of the guarantee period (2 years or 3 years for deep excavations over 1.5m depth) |
The annual statistics for statutory undertakers are summarised in the document below: