Corporate performance on active and healthy lifestyles
The information on this page relates to quarter 3, 2019 to 2020.
4.1.02 Young people in sports scheme
Stage: In progress
Due date: 31 March 2020
Percentage complete: 0%
Status: Amber
Comments:
Total attendances for quarter 3 were 4,746 (6,400) last year.
Total figures for the year to date are now 15,276 (17,580 last year).
There has been an alteration in the programming of events in quarters 3 and 4 in 19/20 which should lead to overall figures balancing out in quarter 4.
4.3.01 Health and wellbeing of children and young people
Stage: Completed
Due date: 31 March 2020
Percentage complete: 100%
Status: Green
4.3.04 Promote sustainable travel
Stage: In progress
Due date: 31 March 2020
Percentage complete: 75%
Status: Green
Comments:
The Local Cycling and Walking Infrastructure Plan was submitted to the Department for Transport. The plan highlighted several routes in the Bracknell urban area that could be brought forward in future.
Officers also continued to work up plans for improvements linked to developments coming forward through the adopted Local Plan including Amen Corner and TRL sites. These will be implemented in the coming years and funded through developer contributions.
4.3.05 Facilitate and promote health improvement schemes
Stage: Completed
Due date: 30 September 2019
Percentage complete: 100%
Status: Green
4.3.06 Support resident run community groups
Stage: Completed
Due date: 31 March 2020
Percentage complete: 100%
Status: Green
4.3.07 Health improvement services
Stage: In progress
Due date: 31 March 2020
Percentage complete: 60%
Status: Amber
Comments:
Physical activity and weight management services continue to be provided as an element of the health improvement programme.
The procurement of a commissioned smoking cessation service is currently underway and is likely to start in quarter 1 2020/21.
4.3.08 Digital services supporting healthy and active lives
Stage: In progress
Due date: 31 March 2020
Percentage complete: 70%
Status: Green
Comments:
Development of the content for THRIVE is ongoing with monthly updates. Soft launch has been completed with key partners such as those from education and early help has taken place.
A well developed communications plan is currently being carried out which includes both digital (social media) and traditional promotion. Promotional work with schools will start in February.
4.4.13 Holly House capital funding
Stage: Completed
Due date: 30 June 2019
Percentage complete: 100%
Status: Green
4.4.14 Accommodation for people with learning disabilities
Stage: In progress
Due date: 30 September 2019
Percentage complete: 50%
Status: Amber
Comments:
There is a transformation project focussed on this aspect of work.
4.4.15 Overpayment recovery contract
Stage: Completed
Due date: 30 June 2020
Percentage complete: 100%
Status: Green
4.6.02 Breaking Free (DAAT online)
Stage: In progress
Due date: 31 March 2020
Percentage complete: 75%
Status: Green
Comments:
This action is on target. There is a push to get more people registered.
4.6.11 Delayed transfers of care and hospital avoidance
Stage: In progress
Due date: 31 March 2020
Percentage complete: 0%
Status: Green
Comments:
The status in quarter 3 has remained positive. Performance over the Christmas period has been particularly effective with a nil return on delays.
4.6.12 Integrated health and care workforce development plans
Stage: In progress
Due date: 31 March 2020
Percentage complete: 20%
Status: Amber
Comments:
We continue to work with the ICS to develop plans.
4.7.02 Child and Adolescent Mental Health Services (CAMHS)
Stage: In progress
Due date: 31 March 2020
Percentage complete: 75%
Status: Green
Comments:
Work is progressing on the Local Transformation Plan with a current focus on early intervention and prevention and embedding an approach in Early Help services - including diversion from the Common Point of Entry of inappropriate referrals.
4.7.06 Support individuals with mental health needs
Stage: Completed
Due date: 30 June 2019
Percentage complete: 100%
Status: Green
4.8.01 Digital inclusion activities
Stage: In progress
Due date: 30 September 2019
Percentage complete: 40%
Status: Green
Comments:
Work is continuing to identify resources available to support the digital inclusion and digital skills development agenda.
4.8.03 Annual learning offer
Stage: Completed
Due date: 31 March 2020
Percentage complete: 100%
Status: Green