Demolishing a building

The process

You need to:

  • send us your completed form, 6 weeks prior to the start of the works
  • include a site plan showing the boundaries and extent of demolition
  • include information such as precautionary measures you intend to put into place to safeguard adjacent buildings and any general public protection measures
  • notify adjacent occupiers and the gas, electric and water suppliers by sending them a copy of the form/demolition notice

We will aim to issue you with a notice within 5 working days. You should not commence demolition until you receive this notice. The notice will contain conditions designed to secure the health and safety of the public.

Copies of the notice will be sent to:

  • gas, electric and water suppliers
  • adjacent occupiers
  • Environmental Health
  • the Fire Service

Bats and birds check

Before undertaking demolition works, appropriate action must be taken to check the building or structure for evidence of bats as a European protected species. Reasonable effort must also be taken to ensure no bird nests are present as these are protected under the Wildlife and Countryside Act 1981.

Relevant guidance is listed below:

Contact Information

Building control