Use this form to request a building site inspection by one of our surveyors, who will check the building works comply with building regulations.
Under Regulation 16 (1), work cannot begin until start notice has been given and at least 2 days have passed since the end of day it was given.
A standard 16 (1) notice is available from Building Control Forms.
Requests for site inspections are viewed at 4pm every weekday afternoon. They are arranged for the next working day unless a later date is requested.
The site inspections usually take place between 8:30am and 2:30pm. Make sure someone is available at the property between these times on the requested date.